Italy: From “Ready-to-Build” to “Ready-to-Construct”: The Hidden Risks of Secondary Permitting
- Despite recent reforms the underlying risk has not gone away.
- Primary authorisation is typically followed by a dense layer of secondary requirements
- Understanding the rules of the game offers a genuine competitive advantage
Two questions dominate this stretch. First, when can a project be considered to have legally “commenced”, so that the authorisation does not lapse? Second, what happens to all the secondary permits, consents and approvals that the primary authorisation does not itself resolve, but that must still be obtained before construction can safely start? Recent reforms, rolled out between 2024 and 2026, are reshaping the landscape, but the underlying risk has not gone away.
„When has a renewable project really ‘started’?“
Ordinary building law is strict. Under the general planning and construction regime, a building permit lapses if works have not effectively started within a fixed period, generally one year, from the grant of the permit. Administrative case law requires something tangible: site organisation, excavation works genuinely directed at the foundations, concrete pouring showing real structural progress, or the erection of load-bearing structures. Preparatory or symbolic activity is not enough.
Renewable energy projects are treated differently. In two judgments of May 2025 (Nos. 4050 and 4051), the Council of State confirmed that missing the start-of-works deadline does not, by itself, justify declaring the single authorisation (autorizzazione unica) lapsed, because the traditional building-law approach cannot apply to renewable plants, which have a distinctive feature: the need to connect to the electricity grid. The start-of-works term is treated as met whenever the developer has taken concrete steps to launch the initiative: securing availability of the project site, accepting the grid connection quote, entering into equipment supply or construction contracts, or obtaining project financing or access to incentives.
This means an authority cannot declare an authorisation lapsed simply because no physical construction site is yet visible: it must first assess the whole picture of preparatory conduct already undertaken by the developer, including any duly justified extension request. The Council of State also confirmed that decadence of an authorisation, being an adverse act, still requires the procedural safeguards ordinarily owed to the developer, absent duly reasoned urgency.
One caveat matters: where the authorisation itself makes the start-of-works term run from a specific triggering event, such as the developer obtaining actual possession of the site through an expropriation procedure, the term runs from that event and not automatically from the date of the authorisation. Getting this anchor date wrong is one of the most common points of dispute between developers and authorities.
Secondary Permitting: The Hidden Part of the Iceberg
The primary authorisation is not the end of the regulatory journey. It is typically followed by a dense layer of secondary requirements: technical prescriptions from the various bodies involved in the authorisation conference, conventions or concession agreements governing interference with public or private assets, environmental compliance steps, and connection-related formalities with the grid operator. None of these is secondary in importance; the label only reflects that they crystallise after the main permitting process closes, and they must all be cleared before the site can safely open.
It helps to distinguish two types of obligation: those that are a genuine condition precedent to opening the site, and those that are broader compliance duties that must be evidenced but not necessarily before the first day of works. Confusing the two is one of the most common planning mistakes.
Case law shows how this secondary layer can generate real friction even after the primary authorisation is uncontested. A municipality that, outside the authorisation conference, unilaterally imposed environmental compensation measures as a precondition to the start of works was found to have acted without competence: such measures for renewable energy plants can only be defined within the conference of services under Article 12 of Legislative Decree No. 387/2003. Similarly, authorities have been found to lack the power to block the start of works by invoking supposed defects in an already concluded and unchallenged procedure, or a generic landscape concern, where the competent regional landscape authorisations had already been issued and gone unchallenged within the statutory term.
Even seemingly minor obligations can carry serious consequences: failing to post a financial guarantee for site restoration before the start of works, or failing to renew that guarantee before its expiry, can trigger decadence of the title, independently of the main authorisation.
A fast-moving regulatory framework, 2024–2026
The framework governing this entire sequence has changed repeatedly over the last two years. Legislative Decree No. 190 of 25 November 2024, in force since 30 December 2024 and known as the “Testo Unico FER”, simplified the administrative regimes for renewable energy production into three tiers: free activity, the simplified authorisation procedure (PAS), and the single authorisation (AU). It also introduced “acceleration zones” with halved authorisation timeframes and the SUER digital platform for managing applications.
The Testo Unico FER has since been amended several times. Legislative Decree No. 178 of 26 November 2025, in force since 11 December 2025, introduced a substantial correction, reinforcing digitalisation through SUER and introducing, among other things, an out-of-court dispute resolution mechanism for permitting disputes, run by Acquirente Unico under ARERA’s coordination. Decree-Law No. 175 of 21 November 2025, converted with amendments into Law No. 4 of 15 January 2026, redesigned the rules on “suitable areas”, consolidating them into new dedicated articles of the Testo Unico FER. More recently, Decree-Law No. 21 of 2026, converted into Law No. 49 of 2026, intervened again on the authorisation framework, strengthening coordination between energy, environmental and building permits and imposing tighter deadlines for starting the related procedures.
The opportunity behind the risk
For an investor looking at the Italian renewables market, this intermediate phase is both the principal risk and the principal source of value. It is here, between authorisation and construction, that much of a project’s real value is decided: knowing how to tell a well-managed secondary permitting process from a neglected one is also knowing how to tell a genuinely sound investment from one that only looks ready on paper.
The 2024–2026 reforms should be read in that light, not as one more obstacle, but as the sign of a system reorganising itself to move faster, with dedicated zones, digital procedures and halved timeframes. Understanding the rules of the game, and the real scope the case law gives developers to challenge authorities that overreach, can turn a phase widely perceived as a bottleneck into a genuine competitive advantage over less prepared entrants into the Italian market.
In a sector where the window to capture incentives, grid capacity and favourable market conditions opens and closes quickly, reaching the construction site even a few months ahead of the competition can be the difference between seizing the opportunity and watching it pass by.