Italy: Virtual Grid Saturation – First Steps Toward New Criteria and Procedures for Grid Capacity Allocation

  • Currently Reserved Capacities to Be Released
  • Access for Concrete Projects Facilitated
  • Transparent, Dynamic, and Measurable System to Be Introduced
Alessandra Matteazzi
Manager
Attorney at Law (Italy)
Svenja Bartels
Partner
Attorney at Law (Germany), Attorney at Law (Italy)
On September 9, 2026, Ministerial Decree No. 291, issued by the Italian Ministry of Environment and Energy Security (MASE), entered into force. The decree is part of the broader reforms initiated by the “Decreto Bollette” and launches the introduction of a new system to overcome virtual grid saturation in the power grid.

Target of the Decree Within the Grid Connection Reform

MASE Decree No. 291/2026 implements the requirements of Art. 7 of the so-called “Decreto Bollette” (Legislative Decree No. 21/2026, converted into Law No. 49/2026) and aims to counteract the phenomenon of virtual grid saturation. This phenomenon is caused by a high volume of grid connection applications for renewable energy projects that often fail to receive permits but effectively block grid capacity “on paper.”

The decree aims to resolve the issue of thousands of connection applications for renewable energy plants (FER) and storage facilities that often never reach the permitting or implementation phase, while simultaneously reserving grid capacity and thereby hindering the development of more advanced projects.

According to MASE, the action will help release currently reserved capacities blocked by connection applications that no longer correspond to viable projects. At the same time, it aims to facilitate access for concrete projects and introduce a transparent, dynamic, and measurable system. The decree is part of a broader reform of connection regulations and a process to simplify and strengthen the permitting system. Available grid capacities are to be publicly accessible, updated quarterly, and managed based on objective and non-discriminatory criteria.

Terna and ARERA’s Role: Key Innovations Under the ‘Decreto Bollette’

As announced in the ‘Decreto Bollette‘, Terna S.p.A., as the operator of the Italian national transmission grid (‘Rete di Trasmissione Nazionale‘, RTN), plays a central role. Terna will have to apply the criteria set out in the MASE Decree as a first step towards implementation.

Given Terna’s role, the decree is initially expected to primarily affect connections concerning capacities or grid elements of the national transmission grid (RTN). However, the extent to which the new mechanisms will apply to distribution grids in the future remains subject to ARERA’s implementing measures.

The reform concerns renewable energy and storage facilities – with the exception of offshore plants.

1. Introduction of So-Called Microzones

Terna is tasked with dividing the national transmission grid into microzones. These are regional or sub-regional areas that reflect the actual infrastructural limitations and operational conditions of the grid.

Taking these real grid restrictions into account, Terna will for each microzone:

  • determine the grid connection points;
  • define the maximum additional integrable capacity; and
  • update the available capacity at least quarterly.

2. Overbooking Mechanism

Terna will be authorized to allocate connection solutions for a specific grid connection point even if the requested power exceeds the theoretically available maximum capacity there. This introduces a regulated “Overbooking” system.

The system allows multiple projects to compete for the same capacity, based on the assumption that only a portion of these projects will receive the necessary permits in time. The mechanism addresses the empirical experience that a significant proportion of projects never reach the permitting or implementation phase despite submitting connection applications.

Accordingly, grid capacity can be allocated beyond the theoretical limits of individual connection points, with final allocation reserved exclusively for projects that meet the requirements of the new system.

3. Open Season Procedure

Access to grid capacities will no longer be based on the current sequential procedure according to the chronological order of connection application submissions. Instead, regular procedures for allocating available capacities (“Open Season“) will be introduced and organized by Terna.

These procedures are to be transparent and non-discriminatory and will take place at least quarterly. Within each tender round, applicants will select one of the connection solutions offered by Terna.

For this purpose, Terna will publish an offer that includes all minimum technical solutions for grid connection available within the Open Season. The offer consists of various connection points of the transmission grid at different substations. Each connection point is characterized in particular by its planning, permitting, and realization status, as well as by the maximum additional capacity that can be absorbed, which is defined for each substation, grid section, and switchgear.

4. Final Allocation of Grid Capacity

One of the most significant innovations, with a considerable impact on the development and realization timeline of renewable energy plants, concerns the final allocation of grid capacity by Terna.

After the completion of the Open Season procedure, Terna issues a certificate of the connection solution to the applicant. However, this document does not yet establish a final claim to grid capacity.

According to the model provided in the decree, grid capacity will only acquire a more stable and priority status upon receipt of the required permit. The detailed operational modalities will be determined within the framework of future implementing regulations by the Italian Regulatory Authority for Energy, Networks, and Environment (ARERA).

Following the logic of the decree, prioritization will in the future be more closely linked to the actual permitting progress of projects. This corresponds to the new principle: “First permitted, first connected”.

Paradigm Shift for Market Participants: The New “First Permitted, First Connected” Principle

The problem of grid saturation is closely linked to the previous processing of connection applications. This was based on a sequential allocation system, whereby each new request was evaluated taking into account already granted and not yet expired connection commitments. It was assumed that these projects would be successfully implemented and would actually utilize the capacity allocated to them within the technical connection solution.

This often leads to a lack of available connection capacities for new projects along the same grid infrastructure, slowing down the development of renewable energies and increasing costs for market participants.

To eliminate this virtual blocking of the grid, the reform is based on a fundamental paradigm shift:

  • from the principle of “first come, first served” (priority for the first submitted connection application),
  • to the principle of “first permitted, first connected” (priority for the first permitted project).

This change in perspective raises, on the one hand, the important question of transitional arrangements for projects already at different stages of development, as well as the related issue of the expiry of existing connection solutions.

On the other hand, the reform presents new challenges for both project developers and investors. They will have to rethink their strategies for evaluating and managing the risks associated with the availability of grid connections, obtaining the necessary permits, and the actual realization of renewable energy plants.

According to MASE, this structural reform will help restore the credibility of the connection system and provide investors with greater legal certainty for investments in Italy.

Outlook

However, the regulatory framework is not yet complete.

The system introduced by MASE Decree No. 291/2026 still requires the adoption of implementing measures by ARERA. These are expected to update the technical and economic connection conditions in the coming months, as well as define the operational and procedural details of the new system for allocating grid capacities for renewable energy and energy storage facilities, with the exception of offshore plants.

Now it remains to be seen how and when the new regulatory requirements will be implemented.