Published on 7. October 2026
Reading time approx. 2 Minutes

Singapore: Advancing Hydrogen-Ready Power Generation

  • Singapore advancing use of hydrogen-compatible combined cycle power plants
  • International collaboration to establish low-carbon hydrogen supply chains
Dr. Paul Weingarten
Partner
Attorney at Law (Austria)
On 29 May 2026, Singapore’s first hydrogen-compatible combined cycle power plant, the Keppel Sakra Cogen (KSC) Plant, commenced commercial operations. The project marks a step in Singapore’s efforts to meet its growing electricity needs while preparing for the future use of lower-carbon fuels. Further investment in generation capacity is already underway, highlighting the continued development of Singapore’s energy infrastructure.

A Milestone for Singapore’s Power Sector

Located on Jurong Island, the KSC combined cycle gas turbine (CCGT) has a generation capacity of 600 MW which increases Keppel Ltd.’s power capacity by approximately 45%. It can co-combust up to 30% hydrogen alongside natural gas and can be modified to operate entirely on hydrogen as supply chains develop. The plant currently operates on natural gas, meaning its compatibility with low-carbon hydrogen provides flexibility for a future transition.

This flexibility is particularly relevant for Singapore, which has limited natural resources. At the end of 2025, 95% of Singapore’s electricity was still generated using imported natural gas. As electricity demand grows, particularly in high-demand industrial and digital sectors such as semiconductors and data centres, the country must balance security of supply with its decarbonisation objectives. Hydrogen-compatible plants offer one potential pathway towards lower-carbon power generation without requiring an immediate departure from natural gas.

Further Hydrogen-Ready Capacity in the Pipeline

Singapore is already taking the next steps towards expanding its hydrogen-ready generation capacity. In April 2026, the Energy Market Authority (EMA) invited proposals for new CCGT generating units of at least 600 MW each. By August, EMA had awarded Tuas Power Generation Pte Ltd the right to build, own and operate a 670 MW CCGT, expected to commence commercial operations by December 2031. The award of the tender for up to two additional units scheduled to commence operations in 2032 is still pending.

Together with the KSC Plant, these plans show Singapore’s preparation against a backdrop of rising electricity demand. EMA projects peak demand to grow by 2.4% to 4.8% annually over the next decade, reaching between 9.6 GW and 11.4 GW by 2031. The additional CCGT generating units will help Singapore accommodate this growth while maintaining a reliable electricity supply.

Outlook: From Hydrogen-Ready to Hydrogen-Powered

The key challenge will be to make the transition from hydrogen-ready infrastructure to the actual use of low-carbon hydrogen viable, including by enabling its delivery to these facilities. Recognising its expected reliance on imports, Singapore’s National Hydrogen Strategy, launched in 2022, identifies international collaboration to establish low-carbon hydrogen supply chains as one of its key objectives. These developments will help shape the role that hydrogen can play in Singapore’s future energy mix.